Ahead of AUSA, editors discuss the MV-75 and the U.S. Army's modernization plans, including long-range fires, air defense, space capabilities and the budget challenges shaping its next steps.
Steve TrimbleGuestVivienne MachiGuest
Joe AnselmoHost
Brian EverstineGuest
Yeah, so the past several months have really been interesting for the MV-75 program, really since we got its name back at Quad A in the spring, the Cheyenne II.

So if we go back to the beginning of the year, then Army Chief of Staff General George said that he expected a prototype to be delivered by the end of this calendar year, which was on a new, very, very aggressive schedule for the program.

Talking to some Army aviation leaders, they basically had no wiggle room, no real room for any – Anything to really happen to meet the schedule.

There was a lot of worry about money running out within fiscal year 26 that would lead to a stop work order.

Text Run has said they'll put some money in to keep it progressing as they await this funding.

I'm really looking forward to discussions at AUSA to get some more clarity on where things stand.

As I mentioned, General George had expected that prototype by two months from now, but that is appearing very unlikely.

About a month ago or so, the head of Army Aviation, General Gill, had an industry day where he said he expected delivery of the prototype at the end of fiscal 27.

So that's basically about a year from now, a little less than a year from now.


So hopefully we'll get a big update on where things do stand on this program and on an overall review of Army aviation that has been going on this year.

That's obviously, I mean, it is kind of the flagship program for the Army aviation community right now.

Yeah, so the past several months have really been interesting for the MV-75 program, really since we got its name back at Quad A in the spring, the Cheyenne II.

So if we go back to the beginning of the year, then Army Chief of Staff General George said that he expected a prototype to be delivered by the end of this calendar year, which was on a new, very, very aggressive schedule for the program.

Talking to some Army aviation leaders, they basically had no wiggle room, no real room for any – Anything to really happen to meet the schedule.

There was a lot of worry about money running out within fiscal year 26 that would lead to a stop work order.

Text Run has said they'll put some money in to keep it progressing as they await this funding.

I'm really looking forward to discussions at AUSA to get some more clarity on where things stand.

As I mentioned, General George had expected that prototype by two months from now, but that is appearing very unlikely.

About a month ago or so, the head of Army Aviation, General Gill, had an industry day where he said he expected delivery of the prototype at the end of fiscal 27.

So that's basically about a year from now, a little less than a year from now.


So hopefully we'll get a big update on where things do stand on this program and on an overall review of Army aviation that has been going on this year.

That's obviously, I mean, it is kind of the flagship program for the Army aviation community right now.
The rest of this transcript — segmented and speaker-labeled, so you land on the exact moment something was said
Search every transcript — by keyword, by phrase, or by meaning, across every show Radar indexes
Trends — what is surging across podcasts, measured against its own baseline
Alerts — when a name you follow appears in a newly indexed episode
No account is needed to search Radar.