Site Selectors Are People, Too
Oct 13, 2026 · 35 min · 8 segments
The era of easy data center approvals is over. Across the country, massive billion-dollar hyperscaler projects are facing unprecedented local opposition. The party of big announcements and giant…
Let's start with the scale of this, because I think a lot of people in our business still treat opposition as a local nuisance.
A handful of loud neighbors, a petition, a tough meeting, and then the project moves forward with a few extra trees along the fence line.
There's a group called Data Center Watch that tracks projects disrupted by local opposition.
In the first quarter of 2026, they counted at least 75 projects worth about $130 billion blocked or delayed.
But that's still more than half of the large developments they tracked in that window.
Now, I want to be careful here because the industry half of my audience is already reaching for the mute button.
A project that slips six months lands in the same column as a project that dies.
At the end of 2025, Data Center Watch counted about 400 active opposition groups.
In some places, people started organizing before anything was even filed.
One tally of elected officials who've opposed data center projects found the split was roughly 50-50 Republican and Democrat.
You've got rural conservatives who care about property rights and farmland sitting next to progressives who care about rate payers and water.
Let's start with the scale of this, because I think a lot of people in our business still treat opposition as a local nuisance.
A handful of loud neighbors, a petition, a tough meeting, and then the project moves forward with a few extra trees along the fence line.
There's a group called Data Center Watch that tracks projects disrupted by local opposition.
In the first quarter of 2026, they counted at least 75 projects worth about $130 billion blocked or delayed.
But that's still more than half of the large developments they tracked in that window.
Now, I want to be careful here because the industry half of my audience is already reaching for the mute button.
A project that slips six months lands in the same column as a project that dies.
At the end of 2025, Data Center Watch counted about 400 active opposition groups.
In some places, people started organizing before anything was even filed.
One tally of elected officials who've opposed data center projects found the split was roughly 50-50 Republican and Democrat.
You've got rural conservatives who care about property rights and farmland sitting next to progressives who care about rate payers and water.
The rest of this transcript — segmented and speaker-labeled, so you land on the exact moment something was said
Search every transcript — by keyword, by phrase, or by meaning, across every show Radar indexes
Trends — what is surging across podcasts, measured against its own baseline
Alerts — when a name you follow appears in a newly indexed episode
No account is needed to search Radar.