Factory Acceptance Testing is where Ed Marszal picks up in Clause 13, starting with an admission: the clause title may be wrong, since 13.2 is called Recommendations when every other point-two clause…
Ed MarszalHost
So we've done all of our design, we've done all of our programming, Now we need to go build it, and that's technically part of clauses 1112, the actual selection of equipment, configuration of equipment, packaging that equipment up, and putting it into a package that's gonna get delivered to the site.

You're just going to buy one off the shelf at your local distributor or have the vendor send it to you.

So factory acceptance test is basically going to be the domain of the SIS logic solver because there's a lot of Customization, shall we say.

It is an engineered product and you want the engineering that they do specifically for you, you need to make sure that that was done properly and you want to do that before you actually physically receive the piece of equipment.

You don't want to pay for it if it's not what you wanted, which is why the factory acceptance clause is usually put in place.

So the typical workflow is you're going to write your safety requirements specifications.

You're going to do this in sufficient detail so that the equipment vendor can actually do their work.

And now on the FAT, I'm going to say this right now, and you just need to remember it for the duration.

I'm talking about the SIS logic solver and it will usually be a PES, programmable electronic system logic solver.

I'm not talking about what's going on at site because obviously it's not going on at site.

So typically we're going to hand over our SRS to the equipment vendor or sometimes to a systems integrator and all of what's going on in the factory acceptance testing isn't actually occurring in the factory where the logic solver was built.

So we've done all of our design, we've done all of our programming, Now we need to go build it, and that's technically part of clauses 1112, the actual selection of equipment, configuration of equipment, packaging that equipment up, and putting it into a package that's gonna get delivered to the site.

You're just going to buy one off the shelf at your local distributor or have the vendor send it to you.

So factory acceptance test is basically going to be the domain of the SIS logic solver because there's a lot of Customization, shall we say.

It is an engineered product and you want the engineering that they do specifically for you, you need to make sure that that was done properly and you want to do that before you actually physically receive the piece of equipment.

You don't want to pay for it if it's not what you wanted, which is why the factory acceptance clause is usually put in place.

So the typical workflow is you're going to write your safety requirements specifications.

You're going to do this in sufficient detail so that the equipment vendor can actually do their work.

And now on the FAT, I'm going to say this right now, and you just need to remember it for the duration.

I'm talking about the SIS logic solver and it will usually be a PES, programmable electronic system logic solver.

I'm not talking about what's going on at site because obviously it's not going on at site.

So typically we're going to hand over our SRS to the equipment vendor or sometimes to a systems integrator and all of what's going on in the factory acceptance testing isn't actually occurring in the factory where the logic solver was built.
The rest of this transcript — segmented and speaker-labeled, so you land on the exact moment something was said
Search every transcript — by keyword, by phrase, or by meaning, across every show Radar indexes
Trends — what is surging across podcasts, measured against its own baseline
Alerts — when a name you follow appears in a newly indexed episode
No account is needed to search Radar.