so this is a great way to sort of read the project management body of knowledge and get some experience with pmp practice questions to really prepare you for your exam let's get into the first question you are managing the apex financial systems upgrade project a confidential project update containing sensitive budget and staffing information was accidentally distributed to a broader stakeholder group than intended what will you do next so something around communications well do we update the communications management plan potentially remember anytime we've got a plan that's our process for how we are managing communications so we could definitely do that let's put that as a high maybe for now Do we update the stakeholder engagement plan? Well, I think it's more around communications.
Even though stakeholder engagement and communications do go hand in hand, I think let's put that as a no.
Do we raise a formal change request to modify project reporting deliverables? We may need to do that if our communications management plan is baselined.
Do we raise the issue or do we update the communications management plan? I think first we're going to raise the issue and manage that because we want to fix what has actually happened.
Then we can update our process and then we may need to go through a change request for that if it's a baselines document.
Monitor communications ensures project and stakeholder information needs are met.
As this is sensitive information, it is an issue that should be addressed first.
so this is a great way to sort of read the project management body of knowledge and get some experience with pmp practice questions to really prepare you for your exam let's get into the first question you are managing the apex financial systems upgrade project a confidential project update containing sensitive budget and staffing information was accidentally distributed to a broader stakeholder group than intended what will you do next so something around communications well do we update the communications management plan potentially remember anytime we've got a plan that's our process for how we are managing communications so we could definitely do that let's put that as a high maybe for now Do we update the stakeholder engagement plan? Well, I think it's more around communications.
Even though stakeholder engagement and communications do go hand in hand, I think let's put that as a no.
Do we raise a formal change request to modify project reporting deliverables? We may need to do that if our communications management plan is baselined.
Do we raise the issue or do we update the communications management plan? I think first we're going to raise the issue and manage that because we want to fix what has actually happened.
Then we can update our process and then we may need to go through a change request for that if it's a baselines document.
Monitor communications ensures project and stakeholder information needs are met.
As this is sensitive information, it is an issue that should be addressed first.
The rest of this transcript — segmented and speaker-labeled, so you land on the exact moment something was said
Search every transcript — by keyword, by phrase, or by meaning, across every show Radar indexes
Trends — what is surging across podcasts, measured against its own baseline
Alerts — when a name you follow appears in a newly indexed episode
No account is needed to search Radar.