Nov 22, 2026
PMBOK 8th Edition Practice Questions 61 to 70 - Pass your PMP and Learn the PMBOK Guide
D
0:00David McLachlanHOST
Hi everyone, welcome back to this section on PMP practice questions where we're going through the PMBOK Guide 8th edition from start to finish and we're answering PMP questions that relate to each section as we go.
D
0:12David McLachlanHOST
This is such a great way to learn the PMBOK Guide 8th edition because we're actually doing it with PMP practice questions so this is really going to help you pass your PMP.
D
0:22David McLachlanHOST
Let's get into the first question in this section and we're already up to a fair way in the PMBOK Guide as you can see question 61.
D
0:29David McLachlanHOST
Elena is managing a warehouse automation project at SLG.
D
0:33David McLachlanHOST
As she monitors the project, she reviews the schedule performance and sees some differences that might require action with a basis for interpreting the current results.
D
0:43David McLachlanHOST
What will Elena use to make the required decisions? okay the schedule basis of estimates now this is the information that we've used it's more of our assumptions so it's what have we based our estimates on is it based on parametric estimating or do we have a commercial database how have you actually done it i don't think that's applicable here so that leaves us with data information and reports do you remember the difference between work performance data that's our raw data so that might be raw information on our schedule how it's going information is tracking it against something else so perhaps things delivered over time and that's going to help us make a decision so it's probably going to be that we turn that work performance information into a report and we send that to stakeholders so they can review it nice and easily but for our purposes let's go with answer C Monitor and control schedule is the process of monitoring project status to update the schedule and manage changes based on actual or forecast performance.
D
1:45David McLachlanHOST
Work performance information is analyzed data compared with the project management plan or project documents or other performance details.
D
1:55David McLachlanHOST
PMBOK Guide 8th Edition, page 53, monitor and control the schedule.
PMBOK 8th Edition Practice Questions 51 to 60 - Pass your PMP and Learn the PMBOK Guide
D
0:00David McLachlanHOST
Hi everyone, welcome back to this series of PMP practice questions where we're going through the PMBOK Guide 8th edition from start to finish and we're looking at practice questions that match up to each section of the guide as we're going along.
D
0:14David McLachlanHOST
It's a great way to become familiar with the PMBOK Guide 8th edition because we're going through the whole thing and we're also going through PMP practice questions so it's a great way to prepare for your exam.
D
0:25David McLachlanHOST
Let's get into the first question.
D
0:26David McLachlanHOST
Jonah is managing a product development project at RLM.
D
0:30David McLachlanHOST
The team needs to clearly organize all deliverables and decompose the work into manageable components to support planning and execution.
D
0:38David McLachlanHOST
What should Jonah do next? And as you can see, we've moved all the way through the basics of project management in the PMBOK guide, through the governance section, and now we're into scope and eliciting those requirements, turning it into scope, and breaking it down into workable or manageable parts that we can assign to a team which is what we're doing here so how are we going to do that do we validate the completed deliverables with stakeholders well we do that at the end and just a key note validating the deliverables is actually when we get sign off from the project sponsor or the paying project customer So that's a key term that we're going to need to know, but it's not applicable for us right now.
D
1:20David McLachlanHOST
Prioritize the features in the backlog for incremental delivery.
D
1:23David McLachlanHOST
We're going to do this in an agile project.
PMBOK 8th Edition Practice Questions 41 to 50 - Pass your PMP and Learn the PMBOK Guide
D
0:00David McLachlanHOST
Hi everyone, welcome back to this series on PMP practice questions where we're going through the PMBOK Guide 8th edition from start to finish while also doing practice questions that align with each of those sections.
D
0:13David McLachlanHOST
So this is probably the best way to get up to speed on the PMBOK Guide 8th edition and really learn that guide and also learn about PMP questions and how to pass those questions on the exam.
D
0:23David McLachlanHOST
Let's get into the next section.
D
0:25David McLachlanHOST
At Northbridge Utilities Group, a project component has recently been handed over to operations.
D
2:15David McLachlanHOST
The final report, updated documents and organizational process assets confirm closure.
D
2:22David McLachlanHOST
That's very handy to know.
D
2:24David McLachlanHOST
We've got the PMBOK Guide 8th edition, page 31 to 33, close project or phase, and page 121 under close project or phase, or that might be the final report actually.
D
2:36David McLachlanHOST
Because remember, in the PMBOK Guide 8th edition, you've got a section at the end for key concepts.
PMBOK 8th Edition Practice Questions 91 to 100 - Pass your PMP and Learn the PMBOK Guide
D
3:19David McLachlanHOST
Co-location is an organisational strategy where team members are physically located to improve communication, relationships and productivity.
D
3:28David McLachlanHOST
PMBOK Guide 8th edition, page 85, lead the team and page 151 and 152 for co-location.
D
3:36David McLachlanHOST
Now that is a great thing to know and we typically use that in an agile team.
D
3:42David McLachlanHOST
So a good thing to go through.
D
4:54David McLachlanHOST
so that could work do we update the stakeholder engagement plan to reflect these updates we might do this or we might use our communications management plan instead so let's put that as a no i think out of these two let's go with a pull communication approach answer c wonderful stuff Monitor and control resourcing, as a process, ensures assigned physical or virtual resources are available as planned.
D
5:22David McLachlanHOST
And pull communications are used for large or complex information, requiring recipients to access content through portals or repositories.
D
5:31David McLachlanHOST
PMBOK Guide 8th Edition, page 87.
D
5:34David McLachlanHOST
Monitor and control resourcing, and page 152, communication methods.
8 More Case Study Questions for new PMP Exam - Agile and Waterfall (9 to 16, Tricky)
D
3:10David McLachlanHOST
Evaluating the exact impact on scope, budget, and timeline allows the project manager to present objective options to governance entities.
D
3:19David McLachlanHOST
And that's from the standard for project management, which is right at the beginning of the new PMBOK guide 8th edition.
D
3:25David McLachlanHOST
that's page 16 assessing project success wow that was quite good all right already we're getting into this one a little bit tricky so how did you go with that one we've got three more questions about this scenario in this specific scenario who holds the ultimate authority to approve the new requirements as project scope and again let's use that same technique here so do we have the product owner prioritizing the current backlog Now, I don't recall seeing a product owner in this scenario.
D
3:59David McLachlanHOST
We've got iterations and a prioritized backlog.
D
5:36David McLachlanHOST
While the project sponsor funds the project, the project is planned in detail with a predictive approach.
D
5:42David McLachlanHOST
Remember that detailed planning over here and altering the scope that impacts the approved project charter requires formal CCB approval.
D
5:53David McLachlanHOST
PMBOK Guide 8th edition, assess and implement changes, page 30.
D
5:57David McLachlanHOST
Now that was a little bit tricky.
8 Case Study Questions for the New PMP Exam (Tricky)
D
8:16David McLachlanHOST
That's in the Standard for Project Management, page 24.
D
8:20David McLachlanHOST
And that's part of the latest Project Management Body of Knowledge, the 8th edition.
D
8:24David McLachlanHOST
And I think we're up to the last question for this scenario already.
D
8:28David McLachlanHOST
We're getting through it.
PMBOK 8th Edition Practice Questions 71 to 80 - Pass your PMP and Learn the PMBOK Guide
D
0:00David McLachlanHOST
Hi everyone, welcome back to this session on PMP practice questions, where we're actually going through the PMBOK Guide 8th edition from start to finish, and we're answering questions as we go along.
D
0:11David McLachlanHOST
This is the absolute best way to read the PMBOK Guide 8th edition and learn it, but also prepare for the PMP exam.
D
0:18David McLachlanHOST
Let's get into the first question, see how we go.
D
0:21David McLachlanHOST
Nina is overseeing a metro expansion project at AU Transit.
D
0:36David McLachlanHOST
Okay, so we're monitoring and controlling the performance of our project and our budget.
D
0:42David McLachlanHOST
Let's have a look.
D
0:42David McLachlanHOST
What are we going to do? Are we performing earned value analysis? with our planned value earned value and our actual cost that's actually looking pretty good we definitely are doing that are we conducting variance analysis this is where we're looking at the variance in different options so maybe what we had planned versus the actual that actually could be very good as well updating the cost baseline to reflect current financial performance well we're really just reviewing these things so far so we're not updating the the baseline yet let's put that as a no and reviewing the work performance report that is a potential answer as well because we've got data information and then reports reports are all of the information in a nice format but we usually send that to our stakeholders so that's probably more for later on even though we are looking at the different variants between these things on our project i think the actual term in the PMBOK guide is actually earned value analysis or earned value management So let's go with answer A and just check.
D
1:48David McLachlanHOST
Okay, thank goodness.
PMBOK 8th Edition Practice Questions 81 to 90 - Pass your PMP and Learn the PMBOK Guide
D
0:00David McLachlanHOST
Hi, everyone.
D
0:00David McLachlanHOST
Welcome back to this session on PMP practice questions that are from the PMBOK guide eighth edition.
D
0:06David McLachlanHOST
So the project management body of knowledge.
D
0:09David McLachlanHOST
This is the latest edition.
D
2:21David McLachlanHOST
They both could be correct.
D
2:23David McLachlanHOST
As this is sensitive information, it is an issue that should be addressed first.
D
2:27David McLachlanHOST
PMBOK Guide 8th edition, page 77, Monitor Communications.
D
2:33David McLachlanHOST
So as you can see, we're working our way through the PMBOK Guide in a really nice way, getting through the communications and stakeholder engagement sections.
Foundations of Project Management | PMBOK Video Course 1.0 | PMP Training
D
0:05David McLachlanHOST
Hi everyone.
D
0:06David McLachlanHOST
Welcome to this series on project management, where we're going through the project management body of knowledge, the PMBOK Guide.
D
0:12David McLachlanHOST
Now this is from the Project Management Institute, and it's basically a huge tome of knowledge.
D
0:17David McLachlanHOST
It's around 800 pages, and it has everything in regards to leading, managing, monitoring and controlling, initiating projects, basically all the way from start to finish.
D
0:28David McLachlanHOST
So we're going to go through all of the different modules in the PMBOK guide and go through them as a video course so that you don't have to necessarily read it all the way through yourself.
D
0:37David McLachlanHOST
There's a lot to get through, so let's get into it.
D
0:40David McLachlanHOST
First of all, project management is not new.
D
3:32David McLachlanHOST
It's aimed at moving an organization from one state, which is the current state.
What is a PMIS? (Project Management Information System) - PMBOK Key Concepts
D
0:05David McLachlanHOST
This is the project management key concepts where we're delving deeper into these concepts from the project management body of knowledge.
D
0:12David McLachlanHOST
And this one in particular is the project management information system or PMIS.
D
0:18David McLachlanHOST
You will hear this referred to a lot throughout the PMBOK guide or the project management body of knowledge.
D
0:23David McLachlanHOST
and you'll also see it in your exam for the PMP or the Certified Associate in Project Management, CAPM.
D
0:29David McLachlanHOST
So what is the Project Management Information System? Well, it's the coherent organization of the information required for an organization to execute projects successfully.