You are the project manager on a retail expansion initiative where detailed planning is managed with regular iterations and a prioritized backlog of work.
What does that sound like? That sounds like we've got detailed planning, but we've also got regular iterations.
The team are at day 74 and have spent $2,900,000 out of a total budget of $3 million.
The phase requires sign-off and approval before the next round of funding is released.
A key regulatory stakeholder who missed earlier planning sessions raises a new mandatory compliance requirement to be completed during the current phase.
The project sponsor disagrees and says that removing any of the current deliverables will breach the approved project charter and put the next round of funding at risk.
What should the project manager do first to resolve the conflict between the regulatory stakeholder and the project sponsor? And what I'm going to do here is I'm not going to reread the case study scenario.
So I'll try also to get rid of any answers that don't make sense to this question and then just refer to the case study scenario if I absolutely have to.
So what do we want to do first to resolve the conflict between the regulatory stakeholder and the project sponsor? Do we ask the team to work on their highest priority items? Well, will that solve the problem? Probably not.
Do we perform an impact analysis? uh that will give us some more information about what's going on between those two deliverables so that's a maybe let's put that one as a maybe do we just go ahead and implement the regulatory change okay now this could be a trick because really we want to get more information so this one's starting to sound a bit better now we want to get more information before making a decision we don't want to just rush straight into things unless it's very clear so we're not going to implement it straight away request guidance from the charters approving steering committee now this one again as project managers we want to do our job as a project manager we don't want to hand it off to someone else if we can help it so that is going to be a very low maybe or even a no and that's really just going to leave answer b so we've done it just by eliminating the other answers let's have a look Wonderful.
Evaluating the exact impact on scope, budget, and timeline allows the project manager to present objective options to governance entities.
And that's from the standard for project management, which is right at the beginning of the new PMBOK guide 8th edition.
You are the project manager on a retail expansion initiative where detailed planning is managed with regular iterations and a prioritized backlog of work.
What does that sound like? That sounds like we've got detailed planning, but we've also got regular iterations.
The team are at day 74 and have spent $2,900,000 out of a total budget of $3 million.
The phase requires sign-off and approval before the next round of funding is released.
A key regulatory stakeholder who missed earlier planning sessions raises a new mandatory compliance requirement to be completed during the current phase.
The project sponsor disagrees and says that removing any of the current deliverables will breach the approved project charter and put the next round of funding at risk.
What should the project manager do first to resolve the conflict between the regulatory stakeholder and the project sponsor? And what I'm going to do here is I'm not going to reread the case study scenario.
So I'll try also to get rid of any answers that don't make sense to this question and then just refer to the case study scenario if I absolutely have to.
So what do we want to do first to resolve the conflict between the regulatory stakeholder and the project sponsor? Do we ask the team to work on their highest priority items? Well, will that solve the problem? Probably not.
Do we perform an impact analysis? uh that will give us some more information about what's going on between those two deliverables so that's a maybe let's put that one as a maybe do we just go ahead and implement the regulatory change okay now this could be a trick because really we want to get more information so this one's starting to sound a bit better now we want to get more information before making a decision we don't want to just rush straight into things unless it's very clear so we're not going to implement it straight away request guidance from the charters approving steering committee now this one again as project managers we want to do our job as a project manager we don't want to hand it off to someone else if we can help it so that is going to be a very low maybe or even a no and that's really just going to leave answer b so we've done it just by eliminating the other answers let's have a look Wonderful.
Evaluating the exact impact on scope, budget, and timeline allows the project manager to present objective options to governance entities.
And that's from the standard for project management, which is right at the beginning of the new PMBOK guide 8th edition.
The rest of this transcript — segmented and speaker-labeled, so you land on the exact moment something was said
Search every transcript — by keyword, by phrase, or by meaning, across every show Radar indexes
Trends — what is surging across podcasts, measured against its own baseline
Alerts — when a name you follow appears in a newly indexed episode
No account is needed to search Radar.