Customer service representatives have requested changes to the portal because they believe it does not adequately support their current processes.
And the requested changes could affect the project's scope, cost and schedule.
already as you can see there's quite a lot going on and so this is going to be our challenge as we go through this particular scenario let's look at the first question based on the scenario what is the most significant challenge currently facing the project now what i'm going to do because my memory is not that great and this is the way that i will handle these questions i'll go through the answer options and see if i can match them up to anything in the question itself resistance from the customer service representatives now customer service representatives have requested changes but are they resisting i wouldn't go that far so i'm actually going to put a no immediately for that one do we look at the defects identified during integration testing yes there are several defects that could affect the planned deployment date but they could we don't know yet we might need to do an impact analysis first so that is a very that's a maybe for that one we'll come back to that unfavorable cost and schedule performance now is it off track we know that we have an earned value of 210 000 and a planned value of 300 so we are behind on our schedule that's true now how do we do the the cost for the cost performance we actually look at the earned value again we've earned 210 so that's what we've created but then the actual cost of 300 000 is what we've spent so we're actually we've spent what we should have spent but we haven't delivered as much as we should have delivered for that particular money so we're actually over our budget as well this one could be a good one i'm going to put that as a high maybe the last one requests to modify the portal interface that is true we do have those requests But is that the most significant challenge? We don't really know yet.
The project is over budget and behind schedule based on the earned value management data.
The other issues are important, but the case explicitly establishes that both cost and schedule performance are currently unfavorable.
Customer service representatives have requested changes to the portal because they believe it does not adequately support their current processes.
And the requested changes could affect the project's scope, cost and schedule.
already as you can see there's quite a lot going on and so this is going to be our challenge as we go through this particular scenario let's look at the first question based on the scenario what is the most significant challenge currently facing the project now what i'm going to do because my memory is not that great and this is the way that i will handle these questions i'll go through the answer options and see if i can match them up to anything in the question itself resistance from the customer service representatives now customer service representatives have requested changes but are they resisting i wouldn't go that far so i'm actually going to put a no immediately for that one do we look at the defects identified during integration testing yes there are several defects that could affect the planned deployment date but they could we don't know yet we might need to do an impact analysis first so that is a very that's a maybe for that one we'll come back to that unfavorable cost and schedule performance now is it off track we know that we have an earned value of 210 000 and a planned value of 300 so we are behind on our schedule that's true now how do we do the the cost for the cost performance we actually look at the earned value again we've earned 210 so that's what we've created but then the actual cost of 300 000 is what we've spent so we're actually we've spent what we should have spent but we haven't delivered as much as we should have delivered for that particular money so we're actually over our budget as well this one could be a good one i'm going to put that as a high maybe the last one requests to modify the portal interface that is true we do have those requests But is that the most significant challenge? We don't really know yet.
The project is over budget and behind schedule based on the earned value management data.
The other issues are important, but the case explicitly establishes that both cost and schedule performance are currently unfavorable.
The rest of this transcript — segmented and speaker-labeled, so you land on the exact moment something was said
Search every transcript — by keyword, by phrase, or by meaning, across every show Radar indexes
Trends — what is surging across podcasts, measured against its own baseline
Alerts — when a name you follow appears in a newly indexed episode
No account is needed to search Radar.