What are the key considerations for planning and then general site management?
0:36
Yeah, on a general scheme, and we're lucky here that we have a full closure, that the biggest criteria is the diversion route for the traffic.
0:47
Is it suitable for the volume of traffic? Is it suitable for all types of traffic going to be using it? We apply for a road closure order six weeks in advance.
0:59
We get approved.
1:00
Then we apply for a speed limit order.
1:03
which reduces the speed of the traffic within the timeframe of the works.
1:08
Then we get that approved.
1:58
Does that present its own challenges?