Paul Abernathy

Nov 23, 2026

9:18
Is there any recourse or what happens next if they're kind of at a standstill?
9:23
Yeah, so there is.
9:25
Remember that the electrical inspector is not always the final say.
9:29
Depending on the jurisdiction, that may be a one-man shop or one-woman shop where she's the AHJ or he's the AHJ.
9:35
He does all the inspections.
9:37
Then that is the top of the food chain, but there's still places you can go.
9:40
With our inspectors, for example, in most jurisdictions that have multiple inspectors, I would tell them that everybody's got a supervisor.

5 MINS LATER

15:03
in the end, have you seen examples where a disagreement actually improved the inspection process? Have you seen that play out in the real world? What lessons can we learn from that?
9:59
What role does grounding and bonding deficiency play in failed inspections, would you say? Yeah.
10:05
Yeah, so this is without the high horse moment, you know, serving on Code Panel 5.
10:10
Right.
10:11
And it's something that in my CMECP program, we really emphasize to our master electricians that are going for that level of certification.
10:19
Grounding and bonding is something that is essential for safety in the performance of the electrical system.
10:26
Bonding jumper sized properly.
10:28
Equipment grounding conductor sized properly.

9 MINS LATER

19:24
So like you talked about the apprentice or whoever's, you know, the younger electrician, checking themselves before they call even their boss in, what would those five things be? Just on a sample, I know every project is different, but what are some key things to keep in mind?
15:26
So what habits would you say, in your experience you've seen so much, what habits separate contractors, electricians who consistently pass the inspections from those who struggle?
15:39
Well, the contractors who consistently do well usually have a few habits in common, right? They walk the job before calling the inspection.
15:46
They do not use the inspector as their punch list, right? I see that all the time.
15:50
That is not what they're there for.
15:53
They keep the approved plans.
15:54
It's one common thing I found.
15:56
I'll tell you, Ellen, a lot of the big contractors, it was amazing to me that they always kept the plans and revised drawings in the same place, and they always knew where to get it.
17:45
So we're kind of generalizing, but let's say how much in advance would you say they need to be getting ready for this and doing this? So like if they have one hour before inspection, before the inspector is coming, like, is it really come down to an hour before the inspector is coming and some of the things they non-negotiables that they would have to get ready? Or should this be done like way before that?