If you're going for your PMP this year, make sure you know about the critical path method and the forward and backwards paths.
The critical path is the sequence of activities which determines the shortest possible project duration.
Now that's easy to see if you're using a program like Microsoft Project where you just click critical tasks and it shows you the longest path on your project.
Now we can find this manually using the forward and backwards pass and we need to find float or any wiggle room or slack for any activities that could move on our schedule and any activities that can't move on our schedule.
And that's the difference between the late start and the early start for any of our activities.
first thing we do is we've got all of our activities and we add their durations so this one's five days this one's five days this one's ten days and so on then we do the forward pass we start with day one add the durations and then minus one so one plus five minus one gives us five at the end then we add one to get to the next one so we've got six and we do it all again add the duration minus one and we get ten and so on Then once we get to the end, we perform the backwards pass, which is just a double check.
minus the duration plus one and so on until we get back to the beginning and then all we need to do is minus the early start from the late start to calculate float as you can see 11 minus 6 the late start minus the early start gives us a difference of five here so we can actually move that five days if we need to we have float or slack But the other activities have no float, so that is actually our critical path.
If you're going for your PMP this year, make sure you know about the critical path method and the forward and backwards paths.
The critical path is the sequence of activities which determines the shortest possible project duration.
Now that's easy to see if you're using a program like Microsoft Project where you just click critical tasks and it shows you the longest path on your project.
Now we can find this manually using the forward and backwards pass and we need to find float or any wiggle room or slack for any activities that could move on our schedule and any activities that can't move on our schedule.
And that's the difference between the late start and the early start for any of our activities.
first thing we do is we've got all of our activities and we add their durations so this one's five days this one's five days this one's ten days and so on then we do the forward pass we start with day one add the durations and then minus one so one plus five minus one gives us five at the end then we add one to get to the next one so we've got six and we do it all again add the duration minus one and we get ten and so on Then once we get to the end, we perform the backwards pass, which is just a double check.
minus the duration plus one and so on until we get back to the beginning and then all we need to do is minus the early start from the late start to calculate float as you can see 11 minus 6 the late start minus the early start gives us a difference of five here so we can actually move that five days if we need to we have float or slack But the other activities have no float, so that is actually our critical path.