Search complete. 5 mentions across 3 episodes found for "Static synchronous compensator".
Oct 28, 2026
Transmission into $avings: Better Connection for Better Rates?
M
63:33Melissa WinneGUEST
I can answer the question.
R
63:37Rick ConantGUEST
There's actually eight STATCOMs planned for the project.
R
63:43Rick ConantGUEST
There are three in Massachusetts and five in Maine, I believe.
R
63:47Rick ConantGUEST
And there are, I think, four phase angle regulators that will be installed in sort of the central 345 KV network.
Grid Enhancing Technologies
M
4:12Michael KimballHOST
northwestern energy pairs advanced power flow control with dynamic line rating on a montana and wyoming transfer path at dollar 26.
M
4:20Michael KimballHOST
5 million federal on dollar 53.0 million total center point energy houston electric lists an advanced transmission system stabilization device at dollar 50.0 million federal duquesne lightless stabilization devices at dollar 22.2 million federal the new york power authority lists a static synchronous compensator at the marcy site dollar 50.
M
4:41Michael KimballHOST
$0 million federal on $270.0 million total.
M
4:45Michael KimballHOST
Together the four draw $148.7 million in federal funds.
9 MINS LATER
M
13:57Michael KimballHOST
How should power flow control companies position? Power flow control companies should position beside dynamic line rating because the one project that names advanced power flow control also names dynamic line rating.
M
14:09Michael KimballHOST
Northwestern Energy's $53.0 million Montana and Wyoming project buys both to raise interstate transfer capability.
M
14:17Michael KimballHOST
Four projects, $148.7 million federal, name power flow or stabilization hardware, and the New York Power Authority's Static Synchronous Compensator carries the largest total at $270.0 million.
M
14:31Michael KimballHOST
One trade commentary lists smart wires among likely beneficiaries without contract evidence.
Battery Storage in Germany: A Grid Operator’s View - 50Hertz
W
15:13Wilhelm KiewittGUEST
And that also leads to the fact that in the transmission system itself, We have to have new assets.
W
15:18Wilhelm KiewittGUEST
We have to have STATCOMs.
W
15:20Wilhelm KiewittGUEST
We have a much stronger AC network to build.
W
15:24Wilhelm KiewittGUEST
So the classical overhead lines that you can see are in the country.