Sep 10, 2026
Toponymic planning: Manchesterism and the Toronto Model
J
25:21Jonathan TinneyGUEST
Yeah, sure.
J
25:22Jonathan TinneyGUEST
So I think when we think about the project we're working on here in Toronto on the Ontario Line, that project, as well as three other priority subway projects in Toronto, was initially designed and their alignments were reworked with the specific purpose of looking at TOC and TOD opportunities within each of those different stations.
J
25:41Jonathan TinneyGUEST
And so when they looked at where those stations occurred, when they looked at the land that was necessary to deliver the station, they were looking at it not just in what's the minimum amount we need to make a project go, but also what opportunities could we create that would then support a future development.
J
25:57Jonathan TinneyGUEST
So in just to the east of downtown Toronto, there's a station called Corktown.
J
27:15Jonathan TinneyGUEST
It takes a lot of pre-work.
J
27:17Jonathan TinneyGUEST
It takes a lot of identification of, you know, what are the structures, what are the key goals that we want to achieve with this program.
J
27:23Jonathan TinneyGUEST
So in the case of, of Ontario Line, the goal was to push for a, a value, you know, maximizing some value opportunities.
J
27:31Jonathan TinneyGUEST
But at the same time, as the program has gone on, it's started to incorporate more focus on some of those community benefits and community amenities, so the, the civic spaces, the parks, affordable housing, other things.
High Speed Rail: Moonshot or Boondoggle?
E
6:25Erin O'TooleHOST
You moved to Toronto around the time the Eglinton Crosstown was being worked on, six years behind, between a billion to two billion over budget.
E
6:35Erin O'TooleHOST
We've seen in the last few weeks news about the Ontario line, that being tripled in cost compared to its budget.
E
6:44Erin O'TooleHOST
We've seen recent reports in the Globe and Mail that Alto will have a cost of $150 billion.
E
6:51Erin O'TooleHOST
And then, of course, in North America, we all know the high-speed rail experience in California.
12 MINS LATER
E
18:42Erin O'TooleHOST
at rudimentary construction and sadly, very poor health and safety for the workers, sadly.
E
18:49Erin O'TooleHOST
But we built it across the country and through the Rocky Mountains faster than we're able to get something across town in the GTA.
E
18:57Erin O'TooleHOST
So is Metrolinx, from your standpoint, learning the lessons of Eglinton, Crosstown, the early challenges with the Ontario line? Is the accountability in that agency? Because they seem to have one of the worst records in recent days, recent years in Canada.
R
19:17Reece MartinGUEST
So I think that Metrolinx is a real enigma.
Hour 3- PM Carney says U.S. officials have changed red lines in trade deal since talks collapsed, which states stand to suffer most in the escalated U.S.-Canada trade war, and Tory’s Take.
J
8:59John MooreHOST
And it reached a new milestone, apparently.
J
9:01John MooreHOST
They laid the deck of it, but it's going to be years before the Ontario line is active.
J
9:07John MooreHOST
So it's going to be years before you're going to see a subway on that bridge.
J
9:10John MooreHOST
You know, I was coming down the Don Valley the other day, and I keep noticing at Millwood that there are these towers that are being constructed.
J
9:17John MooreHOST
So when I got home, I said, what are these towers, Millwood, Don Valley? And it turns out that's for another bridge across the Don Valley Parkway and the valley itself.
J
9:28John MooreHOST
For the Ontario line.
J
9:29John MooreHOST
And then I started looking at maps.
J
9:30John MooreHOST
And to be perfectly honest, I'm going to have to call my friends at Metrolinx and say, somebody help me out here.
373 - Will The Real Poozha Please Stand Up?
G
8:25Gurdeep AhluwaliaHOST
They would have cost $45 to $55 million per station, which is why I guess they didn't do it.
G
8:29Gurdeep AhluwaliaHOST
I will say the new Ontario line that's going up that's under construction, those will have... form-fitting platform edge doors.
G
8:36Gurdeep AhluwaliaHOST
I'm hoping at some point they retrofit all the stations, spend the money, do it right.
G
8:40Gurdeep AhluwaliaHOST
We're supposed to be a global city.