Oct 23, 2026
Water, Power and Data Centers: Understanding the Demands on Infrastructure - EP 153
X
12:08Xander SnyderHOST
In addition to that, there's another 1.9 gigawatts of capacity under construction.
X
12:13Xander SnyderHOST
Now, to prepare for future grid demands, Central Ohio's utility company, AEP Ohio, conducted a study to understand future demands on its electrical grid from data centers.
X
12:24Xander SnyderHOST
And as of early 2026, the number of expected requests, the number of requests that have been made, totaled 17.9 gigawatts.
X
12:33Xander SnyderHOST
And this is of anticipated incremental load capacity, so over 10 times what's currently in place.
P
Unknown podcast
PJM Opens a Separate Lane for SB Energy's 9.6 GW Ohio Campus as Amazon Backs Indiana SMRs — October 21, 2026
Oct 21 · 1 Mention
C
1:24CassidyHOST
The parties are PJM, AEP Ohio Transmission, and 3SB Energy Affiliates.
C
1:31CassidyHOST
The first 800-megawatt phase is already served under Ohio Power's data center tariff, and the filing names OpenAI as the tenant.
C
1:40CassidyHOST
Pike County came up here October 4th with OpenAI's 20-year, 8-gigawatt Ohio lease.
D
1:46DevinHOST
And the generation never enters the interconnection queue.
P
Unknown podcast
NWPPA Morning Brief - Thursday, October 15, 2026
Oct 15 · 2 Mentions
S
1:34speaker_1UNKNOWN
Start with the PJM SoftBank filing.
S
1:37speaker_1UNKNOWN
On October 13th, PJM asked FERC for permission to study how it would connect a roughly 10 gigawatt SoftBank AI data center complex in Ohio paired with 10.2 gigawatts of new on-site gas generation and three new 765 kilovolt transmission lines that AEP Ohio would build.
S
1:57speaker_1UNKNOWN
The filing uses the state agreement approach, a framework that lets a single state sponsor and fund transmission build-outs outside the normal regional cost-sharing process.
S
2:09speaker_1UNKNOWN
Critically, it does not resolve who pays for the new transmission and generation.
S
2:14speaker_0UNKNOWN
That deferral is the design choice worth flagging.
S
2:17speaker_0UNKNOWN
An initial 800 megawatts would be served under an AEP Ohio data center tariff, with the remaining 9.6 gigawatts of load and 10.2 gigawatts of generation phasing in through 2032 at the former Portsmouth uranium enrichment site in Pike County.
S
2:34speaker_0UNKNOWN
Western utilities tracking large load interconnection reform need to understand this framework before similar structures surface in CAISO, SPP West, or bilateral Bonneville Power Administration service questions.
S
2:47speaker_0UNKNOWN
Because deferring cost allocation is not a neutral technical choice.
21 Days to Save an Election: Fire Your Consultants | Monologue Monday
C
31:53Chad LawHOST
And Ohio is already halfway there.
C
31:55Chad LawHOST
State regulators approved a rule for AEP Ohio that makes data centers pay for the new grid they need with an exit fee if they walk away.
C
32:03Chad LawHOST
And Ramaswamy himself already says build them out on old industrial land, not farmland.
C
32:09Chad LawHOST
I mean, the guy's got almost every piece sitting right there on his desk.
A Journey Through Data Centers | A SleepWise Story
G
23:12Grandpa CohenHOST
It is rather like widening the bridge before discovering that the new business needs only a small part of the promised crossing.
G
23:23Grandpa CohenHOST
In July 2025, Ohio's utility regulator approved new arrangements for AEP Ohio's large new data center customers.
G
23:36Grandpa CohenHOST
These included minimum payments linked to committed electricity demand, financial assurances, and charges for leaving early.
G
23:46Grandpa CohenHOST
For the largest covered customers, the minimum billing requirement was tied to eighty-five percent of their contracted demand, even when actual use was lower.
World's Largest Data Center Being Built in Ohio | OVERNIGHT OPINIONS
C
3:08CourtneyHOST
Chairman and CEO of SoftBank Energy Group Corporation claims that this new AI data center will be larger than the entire AI industry right now.
C
3:19CourtneyHOST
SB Energy has already partnered with AEP Ohio to build $4.2 billion in new electrical transmission infrastructure as part of the deal.
C
3:28CourtneyHOST
The company will also be on the hook for computing components that will need to be replaced or refreshed every five years at a cost of $300 million.
C
3:36CourtneyHOST
Just forget for a moment that Ohio is ranked as the most corrupt state in the nation due to a bribery scheme cooked up between politicians and First Energy.