Sep 17, 2026
Eight Billion Dollars of Machines That Do Nothing: Amazon Buys a Stake in Its Own Backup Power, September 17, 2026
C
7:35ChrisHOST
Why does Amazon go to Generac at all here?
L
7:37LauraHOST
Lead time by their own account.
L
7:39LauraHOST
Generac claims 50 to 60 weeks to deliver against an industry standard of roughly 70 to 90 weeks.
L
7:46LauraHOST
And in this particular market, that is the only currency that genuinely matters.
Your Levers Have a Lead Time. The Cliff Doesn't.
J
3:23Jill SteeleyHOST
Because remember, the whole point of shifting your business model is to have more revenue that you are in control of.
J
3:34Jill SteeleyHOST
And so when we want that money to actually pay out, which lever are we going to pull now to pay out when we actually need that money? Because every one of those four levers has a lead time, a gap between the day you pull it and the day a dollar starts to show up in your bank account.
J
3:59Jill SteeleyHOST
And those lead times are wildly different from each other.
J
4:03Jill SteeleyHOST
We're talking 30 days on one end and maybe four years on the other.
J
4:09Jill SteeleyHOST
No one tells you that.
J
4:11Jill SteeleyHOST
So people pick the lever that sounds best, you know, that they might bring up to their leadership team.
J
4:17Jill SteeleyHOST
They pull on it and then wonder in March why the needle hasn't moved.
J
4:23Jill SteeleyHOST
And I want to give you the lead time on all four of the levers.
Caterpillar SVP: AI Doesn't Work Without This Industry | John Shanahan
B
9:34Brad ChildersHOST
And Caterpillar sits in one of the pivotal supply points and supply chains for the industry for power, as well as for oil and gas.
B
9:42Brad ChildersHOST
And lead times have extended substantially.
B
9:46Brad ChildersHOST
What's driving the long lead times right now for engines for power and for the natural gas compression markets?
J
9:53John ShanahanGUEST
At the end of the day, it's, it's purely demand.
J
9:56John ShanahanGUEST
Um, and it's demand on both sides of, of the equation, both on the power generation side as, as well as the gas compression side to, um, to bring the primary source of energy to the generator.
J
12:47John ShanahanGUEST
So it's solely demand driven at this point.
J
12:51John ShanahanGUEST
And I think there's some changes in the behaviors of the industries that we serve where people are starting to look out much further into the future and plan further into the future and look at their needs further into the future than they have in the past.
B
13:11Brad ChildersHOST
One follow-up, for Caterpillar, even with these long lead times, is there an expectation that we will not be able to provide the engines required for power and compression, or are the long lead times indicative of still a market that is going to be adequately supplied based upon CAT's forecasts and expectations to meet market demand?
P
Unknown podcast
CAPM Exam Prep 66, Kanban Metrics — Lead Time, Cycle Time, Throughput
Sep 13 · 7 Mentions
R
0:00Ran ChenHOST
Today we're tackling essential Kanban metrics for the CAPM exam, specifically focusing on lead time, cycle time, and throughput.
R
0:08Ran ChenHOST
Getting these right is critical, as they are frequently tested in scenario-based questions.
R
0:13Ran ChenHOST
Let's start with lead time.
R
0:15Ran ChenHOST
On the exam, you must view lead time from the customer's perspective.
R
0:19Ran ChenHOST
It is the total elapsed time from the moment a request is made until that request is fully delivered to the customer.
R
0:25Ran ChenHOST
Imagine a stakeholder submits a request for a new report feature on June 1st.
R
0:30Ran ChenHOST
The request sits in the product backlog for 10 days.
R
0:33Ran ChenHOST
Your team then starts working on it on June 11 and delivers the completed feature on June 15.
The supply chain fault lines of modern pharma
A
7:45Arvind SinghGUEST
So it could be purification aspects, chromatography, analytical testing, et cetera, where you cannot always add a capacity as quickly as the demand increase.
A
7:55Arvind SinghGUEST
So we try to map these risks during the proposal state itself, which materials are critical, how long are the lead times, is there a qualified second source, um, you know, are the two suppliers procuring from the same upstream manufacturer? We then use our preferred partner network, risk-based supplier qualification, sourcing engagements, et cetera, along with the forward-looking capacity planning to address the highest risks items.
A
8:18Arvind SinghGUEST
And that's-- Basically, the importance here is, is that buying the material is not same as securing supply.
A
8:26Arvind SinghGUEST
The true resilience actually comes from your qualified materials, reliable suppliers, uh, available manufacturing capacity, and enough forward visibility to bring all these elements together to ensure uninterrupted peptide manufacturing and supply.
J
11:19Jennifer Smith ParkerHOST
Okay.
J
11:19Jennifer Smith ParkerHOST
That does make a lot of sense.
J
11:21Jennifer Smith ParkerHOST
So when we're talking about sponsors, and they naturally focus on clinical trials and regulatory milestones, where do you most frequently see a disconnect between a sponsor's expectations and the cold, hard realities of supply chain lead times?
A
11:37Arvind SinghGUEST
So the, uh, the most common disconnect is that su- sponsors understandably plan around their milestones, like the-
Agentic AI and Supply Chain Resilience, with e2open's Pawan Joshi, Northeastern's Nada Sanders and Andre Simha (ex-MSC)
P
11:56Pawan JoshiGUEST
So there are these pockets of visibility and use cases of information that get used, but they don't get used in a holistic manner.
P
12:04Pawan JoshiGUEST
If my supply plan actually assumed my lead time to move from Shanghai to Long Beach is going to get doubled, I would actually create my lead times differently.
P
12:11Pawan JoshiGUEST
I would create my forecast horizon differently.
P
12:13Pawan JoshiGUEST
I'll plan my transportation differently.
#261 - FiberLight: How Fiber Networks Support AI Distribution
B
6:53Bill MajorGUEST
thousands of cable there are thousands of miles of fiber cables for a single project but we're still going to be ordering that much materials because we're going to be adding so much more metro density on our network is we need to get closer to the edge
J
7:09John CelentanoHOST
how have lead times changed though
B
7:11Bill MajorGUEST
oh lead times are you know starting to remind me of the pandemic times uh unfortunately john so You know, it's interesting to see the dynamics today because the demand is real and speed to market is critical.
B
7:28Bill MajorGUEST
You know, some of these hyperscalers, neocloud and data center developers will take lit today with the expectation that a new route would be constructed for them later.
B
7:42Bill MajorGUEST
So there's, you know, a lot of pressure right now on lit fiber manufacturers.
How to pitch expert-led features to The Telegraph
A
22:15Alice WilkinsonGUEST
I mean, we often do sometimes get roundups of experts as well, which is really helpful, especially in, in, um, when there's re- reactive news or news to react to, um, because you can kind of, it's like a menu of experts basically that are kind of ready to go.
A
22:28Alessia HorwichHOST
In terms of lead times, I mean, is it relevant for this? Is there a tight turnaround or do you prefer to take your time? What's the deal?
A
22:36Alice WilkinsonGUEST
I think again, it's really, really depends on the topic.
A
22:38Alice WilkinsonGUEST
Yeah, we had this prostate cancer campaign that we started last summer, and I sat on a feature that was, um, by a prostate cancer surgeon, and we worked on it for ages just because they kept, things kept moving with the, um, the government kept having kind of meetings about what they were doing regarding the prostate cancer screening.
What Really Happens Between a Factory and a Store? The Hidden Supply Chain Explained
M
18:56Marcus BennettHOST
But modern retail replenishment can be much more systematic.
M
19:01Marcus BennettHOST
The retailer may use sales data, inventory records, forecasts, replenishment rules, supplier lead times and other operational information.
M
19:10Marcus BennettHOST
The system can determine that inventory has fallen to a level where additional supply should be ordered.
M
19:16Marcus BennettHOST
That order then becomes another signal traveling backward through the supply chain.
Why are the best bags always SOLD OUT? (NN Podcast)
L
5:21LauraGUEST
So from the beginning, when you're designing the bag, you've already locked down the supply chain of it.
L
5:29LauraGUEST
You know, if you choose what hardware to use, what brand of zipper to use, what color, especially if you're dyeing a fabric specifically for this design, then you already have the list of lead times for all of those.
L
5:45LauraGUEST
And, you know, you have to consider the longest lead time every time.
L
5:50LauraGUEST
So, for example, the longest lead time for this specific product is dyeing a fabric every Special dyeing for the fabric.
12 MINS LATER
A
17:51AaronHOST
You're almost looking at optimizing it.
A
17:52AaronHOST
It's like, cool, as a bag brand owner, I have this product, right? And it's doing very, very well.
A
17:57AaronHOST
Let's break down materially, material by material, the lead times, and then say, all right, where are we most vulnerable? Where is this really taking the most time? And then can that be replaced? And the interesting thing about that is...
A
18:12AaronHOST
I can kind of see that as a double-edged sword though because if you replace it with something that's more accessible, then you risk perhaps your product not being as special.
4 more episodes mention Lead time.
Create an account to see the whole feed, search across every transcript, and follow the entities you care about.