Oct 17, 2026

Peter HambyHOST
6:01
But listen to this construction worker that, uh, CBS21 in Harrisonburg just caught on the street.
J.B. PritzkerGUEST
6:06
When you hear data centers, what comes to mind? I'm working at Homer City building the new data center
Peter HambyHOST
6:11
People say it's only temporary.
Peter HambyHOST
6:12
It's only when they're building it out.
Benjamin HayesGUEST
36:34
Things like a diff- additional infrastructure, water lines, electric lines, infrastructure like that, plumbing, pressure on electric st- electricity markets, uh, the demand itself.
Benjamin HayesGUEST
36:45
Water demand can vary from as much as 20,000 gallons a day at a small site at an existing facility, say the one in Lancaster County or the old printing press, to millions of gallons a day, like, like in Homer City or up in, um, in the, uh, facility up there in the Berwick area.
Benjamin HayesGUEST
37:06
Uh, there's land conversions.
Benjamin HayesGUEST
37:07
They're converting, uh, land, farmland over to industrial facilities, and then there's these long-term financial obligations.
Benjamin HayesGUEST
38:39
Smaller units there can withdraw from public, from a river, um, or a public water supply without even getting that permit there.
Benjamin HayesGUEST
38:46
So the operational water footprint is both a direct use of water at the plant as well as the electricity-related consumption.
Benjamin HayesGUEST
38:54
So those million gallons that you're talking about that, um, on a large hyperscale data center like Homer City, for example, the water consumption could be exceed a million gallons a day.
Benjamin HayesGUEST
39:06
Um, it's not uncommon at all for them to exceed, uh, 500,000 gallons a, a day.
Peter HambyHOST
6:01
But listen to this construction worker that CBS 21 in Harrisonburg just caught on the street.
speaker_3SOUNDBITE_SPEAKER
6:06
When you hear data centers, what comes to mind? I'm working at Homer City building the new data center.
speaker_3SOUNDBITE_SPEAKER
6:11
People say it's only temporary.
speaker_3SOUNDBITE_SPEAKER
6:12
It's only when they're building it out.
Donald TrumpSOUNDBITE_SPEAKER
47:16
You hear data centers, what comes to mind?
speaker_4SOUNDBITE_SPEAKER
47:18
I'm working at Homer City building the new data center.
Donald TrumpSOUNDBITE_SPEAKER
47:20
People say it's only temporary.
Donald TrumpSOUNDBITE_SPEAKER
47:21
It's only when they're building it out.
CassidyHOST
0:18
Welcome to the Data Center Daily for Thursday, October 8th.
CassidyHOST
0:22
Coming up, Google's PowerStack, Amazon at Homer City, Oracle's Wisconsin line back at Square One, an Australian alliance that fell apart, and SpaceX shopping for chip debt.
CassidyHOST
0:35
Black Hills Corp. in its own announcement, as carried by Finviz.
Shane SnyderSOUNDBITE_SPEAKER
0:40
The project, exclusive of additional transmission system expansion investments, is anticipated to be served by a total resource mix of 2.7 gigawatts, including reserve margins, and is planned to begin taking energy service in late 2027 and ramp to the project's peak load in 2030.
CassidyHOST
2:55
Only the 890 is new supply.
CassidyHOST
2:59
Mike Bavto, reporting on the Indiana County filing.
Shane SnyderSOUNDBITE_SPEAKER
3:03
Amazon Data Services, Inc., the company's development arm, filed a preliminary land development plan with the Indiana County Planning Commission on August 28th under the project name PIT-100 Master Plan, laying out 36 data center buildings at the Homer City Energy Campus, 50 miles east of Pittsburgh.
CassidyHOST
3:23
The filing dates to August.
Jordi HaysHOST
26:22
Let's pull this up.
Jordi HaysHOST
26:24
So when you hear data centers, what comes to mind? I'm working at Homer City, building the new data center.
Jordi HaysHOST
26:28
People say it's only temporary.
Jordi HaysHOST
26:30
It's only when they're building it out.
Scott MortonGUEST
35:07
So when you hear data centers, what comes to mind?
Jordi HaysHOST
35:10
I'm working at Homer City, building the new data center.
Scott MortonGUEST
35:12
People say it's only temporary.
Scott MortonGUEST
35:13
It's only when they're building it out.
KaneHOST
41:01
Like sands through the hourglass, so are the days of the United States.
speaker_8SOUNDBITE_SPEAKER
41:07
So when you hear data centers, what comes to mind? I'm working at Homer City building the new data center.
speaker_8SOUNDBITE_SPEAKER
41:11
People say it's only temporary.
speaker_8SOUNDBITE_SPEAKER
41:13
It's only when they're building it out.
speaker_15SOUNDBITE_SPEAKER
57:06
asking, you know, about that.
speaker_15SOUNDBITE_SPEAKER
57:07
So when you hear data centers, what comes to mind? I'm working at Homer City building the new data center.
speaker_15SOUNDBITE_SPEAKER
57:12
People say it's only temporary.
speaker_15SOUNDBITE_SPEAKER
57:13
It's only when they're building it out.
Sean SteffiSOUNDBITE_SPEAKER
11:19
We build the boiler, the internals, the stacks, the tanks.
Julie GrantCORRESPONDENT
11:24
Steffi gave the example of the new data center in Homer City, east of Pittsburgh, a $10 billion project that is reportedly building the largest gas-fired power plant in the country.
Sean SteffiSOUNDBITE_SPEAKER
11:35
This has meant so much to us because for almost five years, we've not taken one new apprentice in.
Sean SteffiSOUNDBITE_SPEAKER
11:42
And just last week, we marked our 230th apprentice that we've taken in the last six months.

6 more episodes mention Homer City.

Create an account to see the whole feed, search across every transcript, and follow the entities you care about.

We value your privacy

We use cookies to understand how you use our platform and to improve your experience. Click “Accept All” to consent, or “Decline non-essential” to opt out of non-essential cookies. Read our Privacy Policy.