Feasibility study

Feasibility study

Search complete. 27 mentions across 9 episodes found for "Feasibility study".

Sep 24, 2026

Paul HarrisHOST
0:27
It's been a very busy few months for Nucor Gold.
Paul HarrisHOST
0:30
In June, you put out a, a pre-feasibility study on your Enchi Gold project in Ghana.
Paul HarrisHOST
0:35
That delivered a $647 million USD after tax, um, net present value at a five percent discount rate, 45% IRR, and that was at a $4,200 per ounce, uh, spot gold price.
Paul HarrisHOST
0:48
Initial CapEx there, about $351 million.

13 MINS LATER

Paul HarrisHOST
13:53
Fair enough.
Paul HarrisHOST
13:54
Let's, uh, look to the future.
Paul HarrisHOST
13:56
You've completed the PFS, you're now working on a feasibility study.
Paul HarrisHOST
13:59
What are some of the key remaining technical work streams that you need to complete to be able to deliver the feasibility study, and what sort of timeline are you looking at to deliver that study?
BethanyGUEST
1:52
Okay.
BethanyGUEST
1:52
Doing energy audits, feasibility studies, helping folks decide what's the next best step for saving energy, improving bottom line, determine if renewable energy makes sense from solar to wind, digesters, geothermal, and then also helping them figure out is there grant money available, is there incentives through utilities, all that kind of stuff to make it affordable.
CoryHOST
2:09
Perfect.
CoryHOST
2:09
I'll probably have you go a little closer with that if you can.
Steve DarlingHOST
0:26
What was this designed to do?
Andrew ConoverGUEST
0:29
Yeah, the intention of this drilling program was to support the feasibility study and also increase the confidence in the deposit through additional drill results.
Steve DarlingHOST
0:41
And so I imagine you're pretty happy with what you're seeing so far.
Andrew ConoverGUEST
0:45
Yeah, thus far it's been very encouraging.
Steve DarlingHOST
1:39
So were you looking at one specific area of that? Like tell me sort of the, because I know it's a bit of a widespread area.
Steve DarlingHOST
1:45
So you were looking at certain areas?
Andrew ConoverGUEST
1:47
The intention of this drilling program was to increase the confidence in the resource as we move into the feasibility study.
Andrew ConoverGUEST
1:55
So this was intended to fill some of those gaps as well as, like I mentioned, increase the confidence in the deposit.
Gregory CroweGUEST
4:41
Now, the reason we made that decision to pivot back is extracts getting excellent results, but it's preliminary and it would require a lot more testing to prove it.
Gregory CroweGUEST
4:53
So with cyanide, we can advance to our pre-feasibility study, hopefully before the year end, as we're trying to get that finalized.
Gregory CroweGUEST
5:01
And that will allow us to then start the permitting process.
Gregory CroweGUEST
5:06
And to reiterate, the permits were never fully shut down after Kinross closed because they never completed a reclamation.
Gregory CroweGUEST
7:28
Silver is a critical mineral.
Gregory CroweGUEST
7:30
Copper is a critical mineral.
Gregory CroweGUEST
7:32
and um there is something called fast 41 which we could apply to but we're too preliminary we're not going to do anything until we get that pre-feasibility study out and we advance to the permitting
Steve YangHOST
7:47
so the pfs you're expecting by view four
speaker_1HOST
14:33
Ah, the ultimate reality check.
speaker_1HOST
14:35
The feasibility study.
speaker_1HOST
14:36
This is the non-negotiable quantitative analysis you run before deploying serious capital.
speaker_0HOST
14:41
The spreadsheet phase.
speaker_0HOST
17:17
So it's about survival.
speaker_1HOST
17:19
Yes.
speaker_1HOST
17:20
The feasibility study isn't designed to suffocate your spirit.
speaker_1HOST
17:23
It's designed to expose the fatal flaws while they are still incredibly cheap to fix on a spreadsheet rather than catastrophic to fix in a courtroom.
Brad RourkeGUEST
6:20
I'll be thinking about that until those assays come through.
Brad RourkeGUEST
6:22
And those rocks won't even, they're sitting on the ground right now because we have to prioritize the resource holes so the geology can catch up to the feasibility study.
Brad RourkeGUEST
6:32
We're essentially done the engineering for the mine.
Brad RourkeGUEST
6:35
It's just the geology we need to catch up.
Shad MarkowitzHOST
7:12
I know you guys have been chomping at the bit for years to get back there, but it makes sense to start with Blueberry because you can drive to it.
Shad MarkowitzHOST
7:18
As you said, it's easy road access, and then it's important for building out the resource model for...
Shad MarkowitzHOST
7:25
Going to the feasibility study.
Shad MarkowitzHOST
7:26
Now there's that middle prong, which is basically stepping out along the trend.
Ken ArmstrongGUEST
7:44
And then on top of that, on the order of another $10 million will be spent this year on pre-feasibility level studies and work.
Ken ArmstrongGUEST
7:52
So metallurgical work, we're doing hydrogeology work, other geotech work on facility locations, the kind of trade-offs that you'd expect to be part of a pre-feasibility study are underway, as well as environmental baseline work.
Ken ArmstrongGUEST
8:07
community engagement, First Nation engagement type work, all the, again, those pieces that are required for the project to enter the EA process.
Ken ArmstrongGUEST
8:13
So let's call it a $30 million budget for this year.
Ken ArmstrongGUEST
10:04
So we basically have mapped it out.
Ken ArmstrongGUEST
10:06
So there's going to be a drill hole through every stope, which is the mined area in our preliminary economic assessment.
Ken ArmstrongGUEST
10:13
And the idea with that is that it should increase the bulk of the ounces in the south zone to the measured category as part of the pre-feasibility study.
Ken ArmstrongGUEST
10:21
We have put out some results like we had a hole just a week ago, this hole 117 that returned 12 grams over just over 12 grams over just over 10 meters.
Ryan SnowGUEST
12:00
that are making the demand for contractor and labor availability scarce and definitely a risk that we're monitoring.
Michael McCrayHOST
12:09
I thought I heard in another interview that you had quite a few feasibility studies that were going to be sequenced out as well, too.
Michael McCrayHOST
12:18
What's the reason for those and how many do you have coming up?
Ryan SnowGUEST
12:21
Yeah, so in May of last year, of 2025, we published five PEAs on all of our projects in the development plan.
Ryan SnowGUEST
12:56
We're also well advanced on the feasibility study for the Cove underground mine.
Ryan SnowGUEST
13:00
So that should be coming out, if not this month, sometime in early Q4.
Ryan SnowGUEST
13:08
And then we're also advancing feasibility studies on the Archimedes underground, which we intend to publish mid-year next.
Ryan SnowGUEST
13:16
And we're working on a pre-feasibility study for the Mineral Point open pit, which is also on that mid-next year timeline.
Ralph RushtonGUEST
0:30
And we're well underway with the engineering study.
Ralph RushtonGUEST
0:34
I think we put out that we're about halfway through our pre-feasibility study.
Ralph RushtonGUEST
0:37
So we've completed the gap analysis.
Ralph RushtonGUEST
0:39
That is, we've identified areas where we need more information.