Oct 21, 2026

Samantha CarrUNKNOWN
99:51
And you'll see on page 11, there's a sub-bullet labeled number four.
Samantha CarrUNKNOWN
99:58
So if the local government representative determines the town lacks resources, capacity, or staffing to review an application, they have 60 days after the receipt request a de novo adjudication by the Energy Facility Siting Board.
Samantha CarrUNKNOWN
100:14
So the EFSB will be the body that will be reviewing projects larger than 25 megawatts for energy generation and larger than 100 megawatt hours for energy storage and the municipality does to opt into that process if it finds that an application falling below those thresholds would cause significant staff or board capacity constraints and that that's kind of the safe hold that you have during that 60 day period.
Samantha CarrUNKNOWN
100:49
If the town were interested in pursuing this there are funds allocated to opt into an Interceptor status from the municipal side to still take part in the application process But not be in the driver's seat so to speak for evaluating the the proposal itself

19 MINS LATER

Samantha CarrUNKNOWN
120:13
um on page 34 there a new definition has been added for small wind facilities specifically to call out wind facilities less than 25 megawatts of energy generation capacity and the reason this definition has been added is that subset of projects qualifies for the consolidated permit process so we're just wanting to make sure folks are aware that IF THEY DO HAVE AN INSTANCE WHERE IT EXCEEDS THAT CAPACITY, IT WOULD NOT QUALIFY FOR THAT PERMITTING PROCESS AND WOULD ESSENTIALLY FOR THE SMALL PROJECTS, THEY HAVE THE OPTION TO STILL OPT INTO LOCAL REGULATIONS OR IF THEY FIND IT FAVORABLE TO DO SO, THEY CAN PURSUE A CONSOLIDATED PERMIT PROCESS.
Samantha CarrUNKNOWN
120:56
FOR PROJECTS LARGER THAN THAT, THERE IS NO ALTERNATIVE CHOICE.
Samantha CarrUNKNOWN
120:59
THEY WOULD BE REQUIRED TO SUBMIT TO THE ENERGY FACILITY SITING BOARD BECAUSE THEY'RE IN EXCESS OF THE SIZE.
Samantha CarrUNKNOWN
121:08
The rest of the edits to this section are largely clerical changes.