Search complete. 33 mentions across 14 episodes found for "Battery management system".

Nov 23, 2026

Vishal KrishnaHOST
2:47
And these are EVs in nature, right? When I say EVs, we are talking about UAVs that use batteries.
Vishal KrishnaHOST
2:53
And these are great battery packs, BMS managed, right? And what I also saw is materials that can withstand high heat, temperatures.
Vishal KrishnaHOST
3:02
And I've seen
Vipul SinghGUEST
3:02
cameras.

16 MINS LATER

Vishal KrishnaHOST
19:29
That's the market.
Vishal KrishnaHOST
19:29
But what is the market for the automotive guys to get into this?
Vipul SinghGUEST
19:33
See, automotive guys mostly are going to provide systems, components and subsystems, motors, BMS, battery systems because there's a lot of common components between EV.
Vipul SinghGUEST
19:46
So they can leverage their existing assembly line to bring something for drone instead of putting up a complete infrastructure from scratch.
Roberto BaldwinGUEST
33:19
It's...
Roberto BaldwinGUEST
33:20
It is a lot of it is now going into the BMS, the battery management system, the sort of software that runs everything, the cooling.
Roberto BaldwinGUEST
33:28
And so, you know, we're still seeing, you know, advances in that.
Roberto BaldwinGUEST
33:32
It's not quite plateauing, but, you know, at some point.
ChristinaUNKNOWN
20:07
All right, number four.
ChristinaUNKNOWN
20:09
Upgrading to a higher amp controller on a stock e-bike can trip the battery's BMS and shut the bike off under hard acceleration.
ChristinaUNKNOWN
20:17
True or false? You can just write T or F, whatever.
ChristinaUNKNOWN
20:32
Or the whole word.
ChristinaUNKNOWN
20:38
Oh, man.
ChristinaUNKNOWN
20:39
It's true.
ChristinaUNKNOWN
20:41
If the new controller pulls more amps than the battery BMS discharge limit amount allows, the BMS cuts power immediately to protect the cells.
RyanHOST
20:49
Yep.
Jerzy KuźmińskiHOST
6:03
There is one more question common to all three models and most important with wide label.
Jerzy KuźmińskiHOST
6:08
Who owns the BMS software? who holds the service tools and parameters and will anyone else ever be given access to them? Because if the brand you are buying from itself buys the BMS from someone else, then in case of a problem, it is only an intermediary.
Jerzy KuźmińskiHOST
6:25
And if it disappears from the market, you are left with a container that nobody can even read.
Jerzy KuźmińskiHOST
6:31
Never mind change its parameters or replace a module.
Jerzy KuźmińskiHOST
9:30
Nobody asks what grade of cell will go into the container.
Jerzy KuźmińskiHOST
9:35
what spread of parameters is permitted within a module and who checks it.
Jerzy KuźmińskiHOST
9:39
And yet it is precisely the spread between cells that decides how quickly the system starts losing usable capacity and how much work the BMS will have to do.
Jerzy KuźmińskiHOST
9:50
The second thing is the age of the cells.
Georg AngenendtGUEST
32:26
which also can shut down entire strings.
Georg AngenendtGUEST
32:28
And especially critical are BMS errors.
Georg AngenendtGUEST
32:31
I mean, we have, for example, seen in one commissioning phase where the BMS, the battery management system, deep discharge battery cells.
Georg AngenendtGUEST
32:39
And this is, of course, really critical because in this case, a copper can go into salvation and this in the end results in a big safety risk.
Sri PopuriHOST
32:46
On the similar lines, George, actually that, for example, the best system is passed every factory test.
George ThomasHOST
8:31
Of course, in this case, this is a lead-acid charger in this UPS.
George ThomasHOST
8:36
If connecting multiple batteries in series of parallel, stick with the same brand and model batch to prevent BMS communications or balancing issues.
George ThomasHOST
8:47
Both of our test batteries are the same rating, so it might be interesting to see how the two different types perform.
George ThomasHOST
8:54
The APC Back-UPS 600 only takes one 12 volt, nine ampere hour battery.
George ThomasHOST
8:31
Of course, in this case, this is a lead acid charger in this UPS.
George ThomasHOST
8:36
If connecting multiple batteries in series of parallel, stick with the same brand and model batch to prevent BMS communications or balancing issues.
George ThomasHOST
8:47
Both of our test batteries are the same rating, so it might be interesting to see how the two different types perform.
George ThomasHOST
8:54
The APC Backup 600 only takes one 12 volt 9 ampere hour battery.
Rosemary BarnesHOST
26:33
The good news is that this might not be allowed for much longer.
CameronSOUNDBITE_SPEAKER
26:36
What's quite hard to decipher when the manufacturers are keeping buffers is you don't know exactly where along that degradation curve you are because ultimately there has been degradation, but they're keeping that concealed from you by fixing, by anchoring that battery health value on the BMS to 100%.
CameronSOUNDBITE_SPEAKER
26:57
So it is problematic.
CameronSOUNDBITE_SPEAKER
26:59
There is supposed to be standardization coming in Europe next year.
Freeman HallGUEST
5:57
Our technology platform, which we call EPS, enables us to deploy batteries in the same pack casing as they come out of a vehicle, essentially sidestepping any additional repurposing costs.
Freeman HallGUEST
6:11
We can essentially communicate with the BMS, the battery management system software, native to the packs.
Freeman HallGUEST
6:18
And we're able to realize greater and greater efficiencies.
Freeman HallGUEST
6:22
But we're seeing our cost to deploy a VC block of best system, probably a good 40%, if not 50% less than the competition.
Jerzy KuźmińskiHOST
14:02
then the UPS, the alarm panel and the control supplies, while the service disconnects and the battery modules go in at the very end.
Jerzy KuźmińskiHOST
14:11
What is verified at this stage? Whether each container's BMS sees all of its racks and reports voltages, temperatures and state of charge correctly, whether installation monitoring works under voltage and whether the gas detection chain inside the container does what it should, opening the ventilation, starting the exhaust fan and sending a disconnection signal to the DC side, all without releasing the aerosol.
Jerzy KuźmińskiHOST
14:35
Every container can pass this stage perfectly and the plant can still not work, because nothing has yet been asked to work together.
Jerzy KuźmińskiHOST
14:43
That comes in the next step, when the components are integrated into one system ahead of the site acceptance test.
Jerzy KuźmińskiHOST
14:49
The EMS has to see every BMS and set limits for the power conversion system.
Jerzy KuźmińskiHOST
14:54
The inverters have to follow the EMS, the plant controller has to talk to the operator SCADA and to the optimizer's platform, And in a fire event, the disconnection sequence has to run across devices in the right order.
Jerzy KuźmińskiHOST
15:06
The inverter first and the battery second.
Jerzy KuźmińskiHOST
15:09
And this is exactly the moment when on any project that was not well prepared contractually, the mutual blaming begins.

4 more episodes mention Battery management system.