Search complete. 36 mentions across 13 episodes found for "KENTUCKY POWER CO".
Oct 17, 2026
Public Miners Just Unplugged $1.5B of Hardware for AI [NEWS]
J
11:24JesseHOST
Next up, TeraWulf expands Musk AI data center campus to one gigawatt.
J
11:28JesseHOST
TeraWulf announced an amended and restated electric service agreement with Kentucky Power growing from five hundred to one megawatt.
J
11:38JesseHOST
More AI there.
J
11:40JesseHOST
It's not stopping.
Reaction to PPI Data, TeraWulf CEO Interview, Global Energy Markets 10/15/26
P
17:13Paul PragerGUEST
We're a co-location company, which means we own the land, we own the energy, we build the building, and we operate the data center.
P
17:21Paul PragerGUEST
So we have long-term predictable cashflow, and we get quality energy from an investment-grade credit like a utility, Kentucky Power, AEP, and we sell it to a high-quality credit, in this case, our customer in Lake Mariner effectively is Anthropic, in the announced deal Hawesville, Anthropic.
P
17:43Paul PragerGUEST
But what the investors also need to understand is that we have an investment-grade backstop.
P
17:49Paul PragerGUEST
In Lake Mariner, it's from Google.
Tuesday, October 13, 2026
B
0:45Bill BurtonHOST
Here's the latest from LPM News.
B
0:49Bill BurtonHOST
Kentucky Power says it intends to build new gas generation in Eastern Kentucky to support a data center project.
B
0:55Bill BurtonHOST
Curtis Tate has more.
C
0:57Curtis TateCORRESPONDENT
In a memo Monday, Kentucky Power told the State Public Service Commission it will no longer seek approval to construct a 450 megawatt combustion turbine at its Big Sandy site.
C
1:07Curtis TateCORRESPONDENT
Instead, the company said it wants the PSC to sign off on a 760 megawatt combined cycle plan in Lawrence County with data center developer TeraWulf paying for the project's construction.
C
1:18Curtis TateCORRESPONDENT
An executive order from Governor Andy Beshear earlier this year prohibits utilities from passing on data center costs to residential customers.
C
1:26Curtis TateCORRESPONDENT
Kentucky Power announced an agreement with the developer last week to offset $100 million in residential winter heating bills over the first 10 years.
C
1:35Curtis TateCORRESPONDENT
The agreement, tied to the Muskie Data campus near Grayson, would save residential customers $25 a month starting in the winter of 2029.
Kentucky Power TeraWulf Deal Adds $100M in Bill Credits
S
0:00speaker_0HOST
Welcome to Sustainability SoundBytes, presented by E&E Leader.
S
0:04speaker_0HOST
Kentucky Power TerraWolf deal adds $100 million in bill credits.
S
0:08speaker_0HOST
An amended Kentucky Power contract doubles TerraWolf's Muskie campus to 1 GW and sends an expected $100 million in winter credits to residential customers.
S
0:19speaker_0HOST
Kentucky Power and TerraWolf have amended their power contract for the Muskie Data Campus, doubling contracted demand from 500 MW to 1 GW.
S
0:29speaker_0HOST
The amendment would send an expected $100 million in winter bill credits to the utility's residential customers.
FERC Keeps PJM's Large-Load Registry, Kills the Curtailment Plan — October 11, 2026
S
6:30speaker_2SOUNDBITE_SPEAKER
The transaction doubles contracted power capacity at the Muskie Data Campus in eastern Kentucky from 500 megawatts, MW, to 1 gigawatt, GW, and accelerates the target delivery of the second 500 megawatt phase from 2030 to 2029, while the initial 500 megawatt phase remains targeted to begin ramping in 2028.
M
6:52MattHOST
TerraWolf doubles Muskie to a full gigawatt with Kentucky Power, and the stock goes the other way.
M
6:59MattHOST
1549 before the announcement, 1365 by October 8th.
M
7:05MattHOST
The market read the same 8K I did.
Kevin Stinnet 10-7-26
J
2:55Jack PattieHOST
... uh, I think we all need to get a consensus as to what it really is, what it really means, and, um, how can it benefit a community.
J
3:03Jack PattieHOST
I mean, this, this week we published a story from Kentucky Power and Terra Wolfe reached an agreement.
J
3:08Jack PattieHOST
It has to be approved by the PSC, but it'll provide electricity for the next 30 years for-
K
3:15Kevin StinnetGUEST
Yeah
Meta Books AI Data Center Chips as an IRS Experiment; Michigan Locks Google Into 20-Year DTE Terms — October 06, 2026
S
7:19speaker_1HOST
The news itself.
S
7:21speaker_1HOST
Amended agreements with Kentucky Power, an A&EP company, signed October 1st and announced Monday.
S
7:28speaker_1HOST
Double Muskie's contracted service from 500 megawatts to 1 gigawatt.
S
7:33speaker_1HOST
The second 500 moves up from 2030 to 2029, subject to the Kentucky Public Service Commission and the utility's construction schedule.
S
7:42speaker_1HOST
The first phase still starts ramping in 2028.
S
7:46speaker_0HOST
And the wires are a real build.
S
7:49speaker_0HOST
InPower reports Kentucky Power is planning a new 765 kilovolt substation called Venator in Boyd County, about two and a half miles of 765 line and two parallel 345 circuits.
S
8:04speaker_0HOST
Final routes aren't picked yet.
TeraWulf Muskogee Site: Latest CORZ, HIVE, BTDR, WULF, GLXY & BTBT Stock News!
A
23:29Anthony PowerHOST
And also the fact that this will pull Phase 2 into 2029 from 2030.
A
23:38Anthony PowerHOST
Now, an amended Kentucky Power Agreement doubles that contract capacity, with the company still evaluating up to 2 gigawatts over time, subject to further utility planning.
A
23:48Anthony PowerHOST
And as I've just mentioned, the second 500 megawatts now targets 2029 instead of 2030, and that will need approval and Kentucky Power's construction schedule.
A
23:59Anthony PowerHOST
The Phase 1 timeline remains unchanged.
A
24:01Anthony PowerHOST
The first 500 is still on target to begin, ramping in 2028 and remember patrick came on the channel and talked about this you know year after year new contracts new delivery looking at 250 to 500 megawatts per year this is certainly looking at 2028 2029 in terms of 500 megawatts of gross power each year being developed into contracts there Now, there's a dedicated substation.
A
24:28Anthony PowerHOST
So Kentucky Power is building a 765KV and a 345KV substation tied into the regional transition network to serve the site.
A
24:38Anthony PowerHOST
So operations at both levels.
A
24:40Anthony PowerHOST
And I think, Bryce, you picked some on this.
Top 5 Co-Lo Deals: Latest WYFI, BTDR, WULF, GLXY, HUT, DRK & RIOT News!
A
47:10Anthony PowerHOST
They've looked at all the updates this week in terms of that additional 500 megawatts, and, um, also the fact it's been brought forward now to 2029.
A
47:20Anthony PowerHOST
Um, it also, uh, reiterates, uh, the agreement with the Kentucky Power also includes 100 million in residential bill credits, generation financing costs, and collateral protections, therefore reducing the rate payer exposure.
A
47:35Anthony PowerHOST
So there's a nice deal in there for, uh, the power company, um, to get this thing, uh, moving in the right direction, something that Paul Prager and the team there have probably been working on for a considerable amount of time, but it's just making sure that that pipeline is a real pipeline and delivering, um, as to their expectations.
A
47:53Anthony PowerHOST
And $37, um, that's an o- overweight rating, um, and one that, uh, uh, Patrick feels, uh, sure that the, the share price, uh, will get to.
TeraWulf Expands Muskie to 1 GW and SpaceX Mulls TSMC for Terafab
C
3:23Colin HarperHOST
Securing the next 500 megawatts and moving its planned delivery into 2029 gives us greater flexibility to meet prospective customer deployment needs.
C
3:32Colin HarperHOST
It also builds on the progress our teams have made with Kentucky Power since we acquired the site.
C
3:38Colin HarperHOST
Additionally, the company continues to evaluate the campus's potential to support up to 2 gigawatts over time, subject to additional utility planning, infrastructure, and agreements.
C
3:51Colin HarperHOST
In an X thread last week, Prager also mentioned that they are seeing a lot of interest in Muskie.
C
8:25Colin HarperHOST
Specifically, they are building out on-site generation battery storage or on-site battery storage for that site to offset some of their load.
C
8:35Colin HarperHOST
One last thing to note here with regards to TerraWolf and the data center rules that are coming out of Kentucky now.
C
8:44Colin HarperHOST
So as I mentioned, they still have to get sign-off from the Kentucky Power Service Commission for this site, this expansion.
C
8:53Colin HarperHOST
Additionally, they are going to have to adhere to new rules that were set forth by Governor Beshear.